Drainage master plan starts over with a new bid, and stormwater impact fees are part of the study

A December 2025 deal with IEA Inc. never produced a contract. Public works staff are writing a new request for proposals for a citywide plan that would also weigh charging new development a stormwater impact fee.

Gwen Mercer· AI-assisted, edited by Jake Team

October 8, 20262 min read

Civic drainage planning - illustration, Jake Team LLC

Princeton is starting over on a citywide drainage master plan, nearly a year after the City Council first moved to hire a firm for the work, and staff want the new study to weigh whether new development should pay a stormwater impact fee.

Public Works Director Rifat Alam laid out the reset at a Sept. 28 council work session, and The Princeton Herald reported on it Thursday. "The prior scope and fees did not fully reflect the city's growth and need," Alam told the council, according to the Herald.

What happened to the first try

According to Alam's memo, engineering firm IEA Inc. briefed the council in November 2025 on updating Princeton's 2018 Master Drainage Study, and the council adopted a resolution for the study in December 2025. No final contract was ever drafted or signed, the resolution did not include a total fee, and no notice to proceed was issued.

Former city staff then went back and forth with IEA over several scope and fee options from February to July without agreeing on one. In May, the city's then-interim public works director told IEA the city intended to repeal the earlier scope of work, at the direction of the mayor and city manager's office, the presentation says.

The new approach

After a review in August, public works staff concluded the plan should cover the whole city plus the drainage areas outside it that feed into Princeton, look at both current conditions and future buildout, and end with a ranked list of drainage capital projects with cost estimates and timelines.

Staff are writing a new request for proposals. Picking a consultant is expected to take about three months, after which the choice comes back to the council for approval. The study itself would take 18 to 24 months from the notice to proceed.

Impact fees on the table

Princeton does not currently charge a stormwater impact fee, the memo says. The presentation notes that Chapter 395 of the Texas Local Government Code allows cities to charge new development impact fees for storm water, drainage and flood control facilities, and that Princeton is eligible. The study would end with options for putting such a fee in place.

Staff also plan a separate in-house computer flood model of the city, which the presentation describes as Princeton's first citywide urban flood risk study. Preliminary modeling is slated to start in the second quarter of 2027 and take about eight months, with a consultant refining it later.

The council's Sept. 28 session was a briefing, and no vote was taken on the drainage plan.

Sources

princetonherald.com

princeton.granicus.com

princeton.granicus.com

princetontx.gov

Share

Gwen Mercer· AI-assisted, edited by Jake Team

Gwen Mercer writes about community life, schools, public safety, and local events in Princeton.